Mall construction at a glance

Headline Photo

U of A Bookstore / ASUA Building

Expected Completion Date: Dec. 22, 2000

Original Completion Date: Nov. 22, 2000

To Be Done During Break: Fire alarm tests still need to be completed. A weekend in mid-December will be set aside for this to be done. Crews are nearly finished with the exterior of the building. Painting of plaster and cleaning of brick on the outside will continue until the completion date. On the inside, carpet will continue to be installed. Painting and concrete staining will also be done.

Possible Delays: Though unlikely, Simplex, the company testing the fire alarms, might not be completed with testing.

"We all have a pretty good understanding that we need to be done by Dec. 22."

- Doug Huie, Swinerton and Walberg Builders student union senior project manager

Food Services Building (former Gallagher Theater site)

Expected Completion Date: March, 2001

To Be Done During Break: Crews will continue with installation of the exterior steel framing.

Possible Delays: The delays are not expected to come from the completion of the building, but rather from the completion of the underground loading dock that will service the building. If the loading dock is not finished in March, food deliveries to the new building could be impacted. Deliveries could be made to the old kitchen and then moved to the new one, but there is a five-foot-grade difference between the two rooms.

"We need to sit down and decide, 'when does it make sense for the union to move?'"

- Doug Huie, Swinerton and Walberg Builders student union senior project manager

New Union Underground Loading Dock

Expected Completion Date: April 2001

Original Completion Date: March 2001

To Be Done During Break: A concrete floor for the loading dock is expected to be poured.

Possible Delays: Rain and late delivery of steel have already delayed the project by a month. Additional delays may occur because steel deliveries have not been completed yet.

Integrated Learning Center

Expected Completion Date: Summer 2001

Original Completion Date: Spring 2001

To Be Done During Break: Much of the work on the ILC will occur outside of the existing fence line. Crews plan to section-off a large portion of the UA Mall, just west of the cactus garden, for installation of new sidewalks and repaving of the bike path. This area is being leveled because it is an area of water ponds that form during rainstorms.

Possible Delays: No delays are anticipated. Crews ran into trouble earlier in the project because of difficulties with concrete work.

- Compiled by Blake Smith


Stories

 


Drugs, alcohol in dorms not a severe problem so far

Effects of construction felt by campus businesses

A Double Life

Ding dong, the old student union's dead

ASUA leaders pleased with progress made so far

New 'outside' editor-in-chief takes reins of the Wildcat

TAs displeased with changes in tuition options

Mall construction at a glance

UA gets $1.2-million grant to support substance abuse treatment

VanTastic replaces Sun Tran, provides shuttle to Wildcat basketball games

KUAT supports KAMP's bid for Low Power FM

Police Beat

Catcalls

World News

Former president Bush has hip replacement at Mayo Clinic

Apartment fire kills three children in Rhode Island

AMA recommends selling morning after pill over-the-counter

Florida Supreme Court agrees to hear Gore appeal

Russia's Population To Decline

Crippled destroyer due in U.S. port next week, Navy chief says

Astronauts take spacewalk to finish installing solar wings

O.J. Simpson involved in altercation with motorist