Bolt problem delays shuttle launch

By The Associated Press

CAPE CANAVERAL, Fla.- NASA called off yesterday's launch of space shuttle Discovery because of last-minute concerns over bolts on the external fuel tank.

The space agency aimed for a tomorrow night lift-off but stressed that the problem must be solved before Discovery can fly. This 100th space shuttle flight is a crucial space station construction mission.

"We think it's prudent to stand down for a day," said shuttle manager James Halsell.

The problem occurred Sept. 8 during space shuttle Atlantis' launch but was discovered only yesterday.

While analyzing film returned to Earth aboard Atlantis two weeks ago, engineers noticed one of the three bolts between the shuttle and the external fuel tank did not retract properly eight minutes into the flight. Photographs showed 2 1/4 inches of the 14-inch bolt sticking out on the tank.

Engineers reviewed the film again yesterday but could not figure out what happened. So the Discovery countdown was halted, just before the start of fueling. The seven astronauts had not yet boarded the shuttle.

Before launching Discovery, NASA wants to understand the bolt malfunction and determine whether it poses a danger. At worst, a protruding bolt could cause the separated tank to tumble and slam into the shuttle.

"I think the word you use would be 'catastrophic,'" said Halsell, himself a shuttle pilot. "I would not want to expose astronauts to that risk."

The troublesome bolt is at the bottom of the Atlantic, along with what is left of the rest of the external fuel tank. The 153-foot, rust-colored tank is jettisoned once the shuttle reaches orbit.

There is evidence of bolt problems on previous flights, including Endeavour's launch in February, said launch manager Bill Gerstenmaier. But the bolts have never protruded like this, he said.

NASA usually has more time between flights to review all the data from the previous, but has quickened its launch pace to build the international space station.

The minimum number of days allowed between shuttle launches is 21. This gap would have been 27 days if Discovery had soared yesterday.

Halsell said NASA remains committed to launching space shuttles seven or eight times a year. Next time, though, the space agency may try to analyze the film more quickly, he noted.

"If there's a success to be shown here, it's that the system does work and that we're able to respond even this close in to the next launch," he said.

Discovery holds two new segments for the international space station, a girderlike truss and a docking port for future shuttle visits. NASA wants these parts installed before the first permanent crew lifts off at the end of the month.